反渗透设备讲解软化水设备管道的连接

A. 管道系统的连接应符合“给排水管道施工标准。”

Connect the A. piping system shall be in accordance with the "water supply and drainage pipeline construction standard."

B. 按照控制口径连接进、出水管。

B. according to the control diameter, pipe connection.

C. 进、出水管应装有手动阀门,出水管之间应安装旁通阀门,一则便于排出安装焊接过程中的残余物,以免污染树脂;二则方便检修。

C. inlet, outlet pipe should be provided with manual valves, installation of bypass valve should be between a water outlet pipe, which is convenient for discharging residue is installed in the welding process, in order to avoid the pollution of resin is easy maintenance; two.

D. 出水口应安装取样阀,进水管道建议安装y型过滤器。

D. outlet shall be installed sampling valve, water inlet pipe is recommended to install y filter.

E. 尽量缩短排水管的长度(<6米),并不得安装各类阀门,在安装过程中只可采用聚四氟乙烯胶带密封。

E. try to shorten the length of the drainage tube (<6 m), and shall not be installed in various types of valves, the installation process can only use teflon tape sealing.

F. 排水管与排水道水面之间必须保持一定的空间,以避免产生虹吸现象。

Keep some space must be between F. drainage pipe and drain the water, to avoid a siphon phenomenon.

G. 各管道之间必须设独立的支架,不允许将管道的重力、应力传给控制阀。

Support of each G. pipeline must be independent, do not allow the pipeline gravity, stress transmitted to the control valve.